Can the lower floor be finished while an upper slab is poured?
Only when the lower frame is no longer moving and the pour above will not wreck it. Overlap is in the programme. It is not a gift to the calendar.

04
Steel before concrete. Brick to the line. Sleeves before the pour. The grey structure is a stage of its own, even inside a turnkey job.
Columns, then the slab, then the next floor, with brick in the order the structure allows. Stairs rise with the floors they serve. The roof is not a leftover. It is the lid on the whole summer.
We look at reinforcement before it disappears. A photograph in a phone is not a record unless someone is responsible for it. The visit is.
If a level is wrong, the next pour waits. Pride is cheaper than a beam in the wrong place. You will hear about a stop. That is the method working.
Finishing does not start to “save time” on a frame that is still moving.
A photograph helps when a named person took it against the drawing. It does not replace the visit. Cover, laps, sleeves, and the line of the column are looked at while they can still be touched.
Brick follows the structure, to the line, with openings where the windows were drawn. A wall built early and then cut for a window is the expensive version of a sheet nobody was holding.
The lid is not spare concrete. Drainage falls, the tank, insulation, and any terrace you mean to use are decided before the last pour. A terrace with no purpose becomes a place nobody sits after April.
Curing is part of the stage. A slab walked the next morning, uncovered and unmarked, is not a completed piece of structure. If the steel on site is not the steel on the drawing, the pour waits.
You will be told when a pour waits. The reason is a level, the steel, or a sleeve still missing. Silence and a later repair are the version we do not use.
Finishing does not start on a frame that is still moving, even when the calendar is tight. The lower floor can overlap only when the programme says the frame above will not wreck it.
Only when the lower frame is no longer moving and the pour above will not wreck it. Overlap is in the programme. It is not a gift to the calendar.
The pour waits. A substitution is not hidden in the concrete and described at handover.
The flight that belongs to the floors being cast, yes. Half a stair and a promise is not a completed frame.
Photographs show the kind of street, house, and commercial building. They are not a record of a named job, and they are not a claim that Zarkaar developed the society around them.